Why projects need one
- The construction loan is reaching maturity and the lender will not extend it
- Costs rose and the remaining loan funds will not finish the building
- The lender is slow to fund draws and the trades are leaving the job
- A buyer has taken over a project someone else started
Why most lenders say no
In Florida, people who supply labor and materials to a project can file liens, and the priority of those liens can relate back to the date the Notice of Commencement was recorded. A new mortgage recorded in the middle of the job is, by default, behind them.
A lender coming in late therefore needs the title company to insure its mortgage as a first lien anyway. That requires proof that everyone who has worked on the project has been paid, and often a formal reset of the Notice of Commencement.
How priority is cleared
- Final or partial lien releases from the general contractor and every subcontractor and supplier who served a Notice to Owner
- A contractor’s affidavit stating who has been paid and who is owed
- Payment of anyone still owed, at closing, from loan proceeds
- In many cases, a Notice of Termination of the existing Notice of Commencement, followed by a new one recorded after the new mortgage
- Title insurance endorsements covering the lender against construction liens
What the lender reviews
Beyond the liens, the lender needs to know what it is lending against. Expect an inspection of the work in place, a line-by-line budget showing what has been spent and what remains, a check of the permit and inspection history with the building department, and a new opinion of the value on completion.
If permits have expired from inactivity, they must be reinstated, and that can require re-inspection of work already covered up.
What to prepare
- The payoff letter from the current lender
- The original budget, all draw requests and what was actually paid
- A list of every contractor and supplier, with releases
- Plans, permits and inspection records
- Current photos of every part of the project
- An updated cost to complete from your contractor, at today’s prices
Be direct about what went wrong
A lender taking over a stalled project wants to understand why it stalled. Say so plainly. A cost overrun with a clear cause is a problem a new loan can fix. A dispute with the contractor or a failed inspection is something we need to hear about on the first call.